Minatitlán Catalytic, Reform Plant

Modernization of the fractionation section, vapor recovery, installation of treatments to sweeten Dry Gas and LPG with DEA ​​and caustics, separation of fines for the recovery of heat from combustion gases and change of the FCC-1 wet gas compressor of Minatitlán, Ver.

Complementary engineering, procurement of equipment and materials, construction and installation of six primary cyclones, six secondary cyclones, full chamber and hemispherical upper cap of the fv-3 regenerator. Includes current top cap removal, cyclones, slide valve, orifice chamber, muffler, instrumentation, and accessories.

Complementary engineering, procurement of equipment and materials, construction, installation, integration, and commissioning of the effluent gas section of the regenerator of the FCC catalytic plant.

Engineering, procurement of equipment and materials, construction, installation, integration, and commissioning of the wet gas compression section and its lubrication, vacuum and condensation services, based on basic and detailed engineering for the modernization of the FCC Catalytic plant.

Detailed engineering, procurement of equipment and materials, construction, installation and commissioning of the ME-101 antifoam injection system.